Citaat:
This is no easy way to say this so we’re just going to give it to you straight: we won’t be able to deliver in October as we had hoped. In fact, if we are 100% transparent, a safe delivery date is February. Yes, February, 2019. We know that while reading this a lot of you will feel upset, let down, or just straight-up angry. That’s a five month delay from our originally estimated delivery date (of September, 2018). We want to explain this and we hope your excitement for the project and your understanding of our situation and our mistakes might help balance out any sorrow or impatience you might feel.
It all comes down to art. We had originally thought that we had enough of a headstart on the art and that we could get a lot more done in a given week than we actually can in reality. Our early estimates were way off. With only a single (amazing) artist there is a limit to what can be done. In case you’re wondering if we’ve just been over here lazing about, we’re happy to report we do have the art of almost 300 cards done (277, as of today, to be exact), and a majority of that is the hard stuff first (customer art, Kickstarter backer portraits, etc). We did originally attempt to speed up the process in a few ways, but the drop in quality was noticeable and so we promptly scrapped that approach. We felt it best if we went back to allowing Mario to work at the pace required to deliver the quality we expect for Seize the Bean (and frankly, anything from Quality Beast). We wanted to wait a bit to get an average of how much card art we could get done in a given week and now that we are confident with that average we’ve taken some serious time to granularly estimate a more realistic timeline and reconfirm it not only with our team but with our manufacturer, too. Here it is broken down:
September 3rd, 2018 = All Files Uploaded to Panda (our manufacturer)
September 14th, 2018 = Design Verification Complete (meaning, all files 100% approved)
September 28th, 2018 = Pre-Production Copy Arrives (for our feedback and proofing)
October 8th, 2018 = Mass Production Begins
November 19th, 2018 = First Mass Production Copy Arrives (for last minute emergency checks)
December 3rd, 2018 = Mass Production Finished & Assembly Begins
December 17th, 2018 = All Games Leave the Factory
As you can see, we’d have the game on its way this year and even beat the holiday season shipping crunch, however, it would be on an estimated 6-week-boat-ride to each fulfilment center and then be on its way to you. This is why we estimate an arrival time of February. Depending on where you are in the world (and if games get slowed down in customs at certain fulfilment centers) it could be a bit faster or slower.
The only three things we can do about this timeline is to communicate it transparently to you all (as we are doing now), apologize for it, and learn from it. We are truly sorry if this upsets anyone but this does not change a single thing about the project: we are dedicated to delivering you a extremely fun, high quality game dripping with theme. And we hope you will stand by us on this wild ride which is a learning process for us too!
Niet 1, niet 2, maar een dikke 5 maanden vertraging erbij! Ben hier behoorlijk teleurgesteld over